Topic: Updated gas works schedule and contact numbers
Posted by: Mark Julian Raymond
Date/Time: 29/07/19 21:28:00

A most interesting letter came through the letter box this weekend,
From Polly Gourlay, Project Manager for Cadent it outlines the project timeline as follows:
Gas Mains Replacement - South Ealing Road
I am writing to provide a further update on the  works currently underway on South Ealing Road.
We have delayed the Phase 2 works by 7 days so as to allow the commissioning of the Phase 1 works and removal of the mulitway signals near Carlyle Road.
The works are progressing well and we are still on schedule.
Unfortunately we needed to suspend the north and south bus stops b/w Carlyle Road and Darwin Road however we are hoping to put two temporary stops in place  next week and reinstate the bus stops by Monday 5th August.
We hosted the community consultation evening on Monday 22nd July and had good turnout of local councillors and residents. If you missed the event please get in touch and we will be happy to answer any questions.
South Ealing Road Phasing
Phase 1 - starting at Greenlawn Lane and finishing at South Road, this will be under multiway signals with side road closures at Occupation Lane, South & North Road. There will also be parking suspension throughout this section.
Phase 2 - Junction of Popes Lane. This will be completed over the summer 2019 holidays and 4 way lights will be in place,
Phase 3 - Temple Road - South Ealing Station. This will involve parking and bus stop suspensions, side road closures and potential multiway signals.
Phase 4 - South Ealing Station (north side of bridge) - Church Lane, side road closures, further traffic management to be agreed with local authority - please read further updates to come.
Our gas mains replacement programme is essential to replace the Victorian gas pipes, so we can continue to provide safe and reliable energy to homes and businesses and will reduce the amount of unplanned workto repair aging gas pipes. Please be assured we remain committed to doing this work with the minimum of inconvenience.
If you would like more information, please callor email our Community Relations Team on 0800 389 8281 or info@communityrelations.co.uk

Yours faithfully,


Entire Thread
TopicDate PostedPosted By
NO MORE LEAKS! Giant gas main replacement project gets going in South Ealing27/06/19 16:06:00 Mark Julian Raymond
   Re:NO MORE LEAKS! Giant gas main replacement project gets going in South Ealing27/06/19 19:47:00 Susan Kelly
      Re:Re:NO MORE LEAKS! Giant gas main replacement project gets going in South Ealing28/06/19 08:42:00 Lee Page
      Slight Correction, first definite sections "booked"28/06/19 12:49:00 Mark Julian Raymond
         Re:Slight Correction, first definite sections "booked"28/06/19 13:48:00 Susan Kelly
            Re:Re:Slight Correction, first definite sections "booked"28/06/19 22:57:00 Susan Kelly
               Re:Re:Re:Slight Correction, first definite sections "booked"29/06/19 07:17:00 Philippa Bond
   Re:NO MORE LEAKS! Giant gas main replacement project gets going in South Ealing04/07/19 17:23:00 Susan Kelly
      Prroject preparation following TV survey perhaps?06/07/19 16:31:00 Mark Julian Raymond
         Re:Prroject preparation following TV survey perhaps?06/07/19 17:10:00 Susan Kelly
            Re:Re:Prroject preparation following TV survey perhaps?09/07/19 17:38:00 Mark Julian Raymond
               Work progresses Occupation Lane closed12/07/19 17:35:00 Mark Julian Raymond
   6 weeks of contraflow, for starters15/07/19 11:12:00 Mark Vale
      Re:6 weeks of contraflow, for starters15/07/19 17:52:00 Susan Kelly
         Updated gas works schedule and contact numbers29/07/19 21:28:00 Mark Julian Raymond
            Avoid Popes Lane/South Ealing Road/Little Ealing Lane Junction - temporary traffic lights, congestion05/08/19 16:47:00 Mark Julian Raymond
               They've got as far as the Co-op, clever strategies, Victorian Enginerring worth viewing22/08/19 12:52:00 Mark Julian Raymond
                  Quality work09/09/19 20:24:00 Mark Julian Raymond
   Traversing the London Underground bridge next to South Ealing tube station Saturday 19th October19/10/19 22:04:00 Mark Julian Raymond
      Re:Traversing the London Underground bridge next to South Ealing tube station Saturday 19th October23/10/19 09:26:00 Simon Wycombe
   Re:NO MORE LEAKS! Giant gas main replacement project gets going in South Ealing23/10/19 19:44:00 Robert Marrill